Vakuumsäker · England · Workshop exercises
Vacuum drainage for plumbers
Use a drawing, the relevant installation instructions and a sample test record. Work from a training drawing or on an approved training rig.
1. Find the point of connection
A new building is to connect to an Anglian Water vacuum sewer. The drawing shows a foul drain, a surface water drain and an existing vacuum collection chamber. Mark the proposed route and list what you need the sewerage undertaker to confirm.
What to look for
Show the foul drain running by gravity to the designated collection chamber. Keep surface water separate. Ask the undertaker to confirm the connection point and capacity before work starts. Then sketch a separate example of a vacuum WC inside a building and mark where vacuum begins in each example.
2. Check the work before backfilling
The installed drain enters the chamber at a different level from the drawing. The trench is due to be backfilled. What do you do from a safe working position?
What to look for
Record the discrepancy and refer it to the site supervisor. Check the agreed levels, route, connection and inspection requirements against the approved drawings and undertaker’s requirements. Identify which section is to be tested, the test method and where to find the acceptance criteria.
3. Report a fault and hand over
A fault is reported after the connection is made. The customer says that two properties are affected. What do you pass on to the operator?
What to look for
Record the locations, time, symptoms and any accessible readings you are authorised to take. Ask the operator to confirm the extent of the fault. Follow the site’s safe system of work and leave chamber entry to authorised personnel. Hand over the test records and as-built drawings.
Practical assessment · Trace a loss of vacuum
On the training rig, vacuum recovers more slowly after a discharge than it did during the baseline run. Air can still be heard entering after the interface valve should have closed. On the drawing, mark the gravity inlet, the valve, the gauge point and the line to the station. Show how air and foul water move when the valve opens.
Show how you would make the rig safe before opening anything. To pass, identify the measurement point, separate what you observed from what you suspect, and record the tightness test and functional check separately.
Assessor notes
Compare the reading with the baseline for this rig. A valve failing to seal and a leaking joint are both possible causes of vacuum loss. Explain how the rig procedure lets you tell them apart. If the line passes its tightness test but fails to clear during operation, check the installed pipe profile against the drawing and refer to the valve instructions for functional checks.